Offshore Wind Cables Deserve a Front Seat in Early Layout Optimization
The Hidden Cost Driver in Offshore Wind Projects
In offshore wind development, inter-array and export cables represent one of the most frequent—and costly—sources of failure. Despite their outsized impact on long-term profitability, they are often overlooked in favor of higher CAPEX elements such as turbines and foundations.
With mean times to repair (MTTR) ranging from 50 to 60 days, and failure rates reaching 0.0007/km/year (TenneT), the financial consequences of unoptimized cable layouts can reach up to €100 million in lost revenue, particularly when outages coincide with high wind and electricity prices.
A Shift in Mindset: Optimizing Cables from Day One
Youwind’s new cable visualisation functionality—integrated into its layout generator and optimizer (formerly Pixel Park)—gives offshore wind developers the tools to simulate, assess, and refine cable networks at the earliest design stages.
With this update, users can:
- Generate optimised inter-array and export cable routes
- Simulate failure scenarios and related OPEX impacts
- Build layout resilience by including redundant paths and meshed grid structures
- Evaluate how design choices influence long-term bankability and LCOE calculation
This shift supports smarter, scenario-based wind farm layout decisions grounded in technical reliability and financial foresight.
Cables: Low CAPEX, High Risk
While cables typically account for a smaller share of upfront costs, their OPEX impact—especially during failures—can ripple through project budgets and investor confidence.
“Cables represent a lower CAPEX cost compared to turbines or foundations, but they can trigger enormous downstream losses if not properly designed,”
— Edvald Edvaldsson, CTO and Co-Founder, Youwind Renewables
That’s why Youwind’s cable tools consider key parameters such as:
- Cable length and routing
- Voltage class, cross-section, and material
- Number of turbines per string
- Redundancy interlinks and offshore substations
These variables feed directly into the platform’s bankable yield assessment engine—helping users understand the real-world risks and rewards of each configuration.
A Comprehensive Layout Ecosystem
Youwind’s platform allows users to model all key components—from turbines and foundations to substations and cabling—within one seamless wind farm planning tool.
Available for both floating and fixed-bottom installations, the new cable module supports:
- Rapid design iteration
- GIS constraint analysis incorporating bathymetry, environmental zones, and routing corridors
- Collaborative workflows for engineers, analysts, and financial teams
By integrating failure simulation and cable loss visualisation into the early design process, Youwind enables developers to make data-driven decisions in wind energy that are robust, resilient, and ready for tomorrow’s interconnected offshore landscape.
Request a demo
Get a first-hand look at how Youwind can support your wind energy management and development, whether onshore or offshore. Fill out the form and we’ll be in touch to schedule your personalised demo.